Duration-Based Project Planning
Which came first, the chicken or the egg? Some might think resolving this conumdrum is equivalent to deciding the best approach to building a project schedule. Which is better, building a schedule based on resource availability or fixed (time) durations? But, unlike the first question, the second yields a clearly superior approach.
Resource-Driven Durations
“Resource-driven durations” is when activity durations are calculated based on the availability of resources. Unfortunately, this approach does not involve the actual team members’ commitment/accountability for activity durations and are often inaccurate due to:
- Other resource commitments not accounted for in the system.
- The durations of some activities that might be relatively fixed and not determined by resource requirements/availability.
- Software (e.g. Microsoft Project) that potentially changes the activity durations every time the schedule is re-calculated, leading to a highly unstable schedule.
Fixed Durations
For these reasons, we ascribe to using “Fixed durations” – when the team member is responsible for managing the activity estimates, while taking resource requirements/availability into consideration. It is not an overstatement to say this approach is infinitely better in that:
- It builds team commitment/accountability for activity durations.
- Duration estimates tend to be more accurate, because the activity manager considers all factors affecting the duration.
- Microsoft Project does not change the estimated duration, and a revised duration estimate can be entered manually if needed.
- This approach maintains a stable schedule.